36 mnd fornyelse av sertifikater på ACS servere i ACS og AMAC kabinett og tilstandskontroll ERTMS
SA-RAC-0000-02
36 måneders intervall
Oppgave | Oppgavebeskrivelse | Lang-beskrivelse | Intervall | Myndighetsnivå | Type FV |
---|---|---|---|---|---|
1000 | Oppdatering av fastvare for ACC-AP-kontroller |
Kontakt Siemens for å kontrollere at systemet bruker nyeste firmware. Om nødvendig, oppdater i henhold til "Installation Instructions SiPass Access Control Management System" (2000002799) kapittel 5.3.3. Se dok. 2000000381 "Drifts- og vedlikeholdsmanual tilgangskontrollsystem, distribuerte komponenter", kapittel 6.5.7 "Oppdatering av fastvare for ACC-AP-kontroller" på side 133 for prosedyre. |
36 md | Lav | PO |
1010 | Central system hardware: Inspection |
a) Inspect the hardware’s overall mechanical condition to ensure there is no external damage. b) Check all physical mountings are intact and properly fastened to the server and server rack. c) Ensure that none of the servers warning lights is active. d) Ensure that all cable connections are in place, and there is no risk of them becoming disconnected. e) Inspect the area where the hardware is installed for signs off water leakage or other substances that might damage the hardware over time. Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1 "Central system hardware: Inspection" på side 77 for prosedyre. |
36 md | Høy | TK-V |
1020 | Central system hardware: Cleaning |
Check for dust on the servers or in the cabinet. Check for dirt on the servers. Check the air filters for dirt / damage Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1 "Central system hardware: Cleaning" på side 77 for prosedyre. |
36 md | Høy | TK-V |
1030 | Central system hardware: Planned reboot of the virtual servers |
Reboot the virtual servers Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1.1 "Central system hardware: Planned reboot of the virtual servers" på side 77 for prosedyre. |
36 md | Høy | PO |
1040 | Central system hardware: Planned reboot of the physical servers |
Reboot the physical servers Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1.1 "Central system hardware: Planned reboot of the virtual servers" på side 77 for prosedyre. |
36 md | Høy | PO |
1050 | Central system software: Inspection |
Verify that the installed software is still supported by the manufacturer. If the software is obsolete, it is recommended to plan and perform upgrade to a newer version. Inspect that there are no active warnings. Inspect logs for signs off operational problems. Verify system backup is running Verify SiPass full database backup is running with a 30-day history available. If not, request the neces-sary repair. Verify SiPass purge log every 180 days policy, is still valid. If not, request configuration change. Verify date and time settings, correct the setting if incorrect. Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.2 "Central system software: Inspection" på side 78 for prosedyre. |
36 md | Høy | TK-V |
1060 | Visual inspection of the cleanliness of computer cabinet and components |
Check whether the cabinet and its components are clean and undamaged. Se dok. 2000006700 "Operating and Service Manual Generic Master CCF Cabinets" kap 8.3.1 "Visual inspection of the cleanliness of computer cabinet and components" på side 67 for prosedyre. |
36 md | Høy | TK-V |
1070 | Functional test of computer cabinet doors |
Check whether the cabinet doors close easily and tightly. Se dok. 2000006700 "Operating and Service Manual Generic Master CCF Cabinets" kap 8.3.2 "Functional test of computer cabinet doors" på side 67 for prosedyre. |
36 md | Høy | TK-F |
1080 | Visual inspection of cables and connectors |
1) Check whether the earthing cables are connected from the cabinet doors to the cabinet frame. 2) Check whether the earthing cable of the cabinet is fixed and not torn off. 3) Check whether the contact clips and cable straps are fixed properly. 4) Check whether the incoming and outgoing cables are laid and fixed properly. 5) Check whether all connectors are plugged in properly, fixed and labeled. Se dok. 2000006700 "Operating and Service Manual Generic Master CCF Cabinets" kap 8.3.3 "Visual inspection of cables and connectors" på side 68 for prosedyre. |
36 md | Lav | TK-V |
1090 | Visual inspection of CoolBlastT 230V HP fan assembly |
1) Check whether the fan assembly is operational: the green LED “system ok” on the front of the fan must light up. 2) Check that the fan speed operates in the required range: the red LED on the front of the fan is off. 3) Check whether the fan assembly is making unusual noises. Se dok. 2000006700 "Operating and Service Manual Generic Master CCF Cabinets" kap 8.3.3 "Visual inspection of CoolBlastT 230V HP fan assembly" på side 68 for prosedyre. |
36 md | Lav | TK-V |
1100 | Visual inspection of AC115-230V/DC24V fan assembly |
1) Check whether the fan assembly is operational: the green LED on the front of the fan must light up. 2) Check that the fan speed operates in the required range: the red LED on the front of the fan is off. 3) Check whether the fan assembly is making unusual noises. Se dok. 2000006700 "Operating and Service Manual Generic Master CCF Cabinets" kap 8.3.3 "Visual inspection of cables and connectors" på side 69 for prosedyre. |
36 md | Lav | TK-V |
1110 | Functional test of AC115-230V/DC24V fan assembly |
Press the blue button. The red LED must light up. Se dok. 2000006700 "Operating and Service Manual Generic Master CCF Cabinets" kap 8.3.3 "Functional test of AC115-230V/DC24V fan assembly" på side 70 for prosedyre. |
36 md | Høy | TK-F |
1120 | Central system software: Renew certificates |
Before the SiPass certificates expire (default every 1170 day), the certificates need to be renewed. Contact Siemens Mobility support. Se dok. 2000000381 "Drifts- og vedlikeholdsmanual tilgangskontrollsystem, distribuerte komponenter", kapittel 6.5.7 "Oppdatering av fastvare for ACC-AP-kontroller" på side 133 for prosedyre. |
36 md | Lav | PO |
Oppgave: 1000
Oppgavebeskrivelse
Oppdatering av fastvare for ACC-AP-kontrollerLang-beskrivelse
Kontakt Siemens for å kontrollere at systemet bruker nyeste firmware. Om nødvendig, oppdater i henhold til "Installation Instructions SiPass Access Control Management System" (2000002799) kapittel 5.3.3.Se dok. 2000000381 "Drifts- og vedlikeholdsmanual tilgangskontrollsystem, distribuerte komponenter", kapittel 6.5.7 "Oppdatering av fastvare for ACC-AP-kontroller" på side 133 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Lav
- Type FV PO
Oppgave: 1010
Oppgavebeskrivelse
Central system hardware: InspectionLang-beskrivelse
a) Inspect the hardware’s overall mechanical condition to ensure there is no external damage.b) Check all physical mountings are intact and properly fastened to the server and server rack.
c) Ensure that none of the servers warning lights is active.
d) Ensure that all cable connections are in place, and there is no risk of them becoming disconnected.
e) Inspect the area where the hardware is installed for signs off water leakage or other substances that might damage the hardware over time.
Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1 "Central system hardware: Inspection" på side 77 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV TK-V
Oppgave: 1020
Oppgavebeskrivelse
Central system hardware: CleaningLang-beskrivelse
Check for dust on the servers or in the cabinet. Check for dirt on the servers. Check the air filters for dirt / damageSe dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1 "Central system hardware: Cleaning" på side 77 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV TK-V
Oppgave: 1030
Oppgavebeskrivelse
Central system hardware: Planned reboot of the virtual serversLang-beskrivelse
Reboot the virtual serversSe dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1.1 "Central system hardware: Planned reboot of the virtual servers" på side 77 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV PO
Oppgave: 1040
Oppgavebeskrivelse
Central system hardware: Planned reboot of the physical serversLang-beskrivelse
Reboot the physical serversSe dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.1.1 "Central system hardware: Planned reboot of the virtual servers" på side 77 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV PO
Oppgave: 1050
Oppgavebeskrivelse
Central system software: InspectionLang-beskrivelse
Verify that the installed software is still supported by the manufacturer. If the software is obsolete, it is recommended to plan and perform upgrade to a newer version.Inspect that there are no active warnings.
Inspect logs for signs off operational problems.
Verify system backup is running
Verify SiPass full database backup is running with a 30-day history available. If not, request the neces-sary repair.
Verify SiPass purge log every 180 days policy, is still valid. If not, request configuration change.
Verify date and time settings, correct the setting if incorrect.
Se dok. 2000002452 "Maintenance Instructions SiPass Access Control System", kapittel 7.2 "Central system software: Inspection" på side 78 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV TK-V
Oppgave: 1060
Oppgavebeskrivelse
Visual inspection of the cleanliness of computer cabinet and componentsLang-beskrivelse
Check whether the cabinet and its components are clean and undamaged.Se dok. 2000006700 "Operating and Service Manual Generic
Master CCF Cabinets" kap 8.3.1 "Visual inspection of the cleanliness of computer cabinet and components" på side 67 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV TK-V
Oppgave: 1070
Oppgavebeskrivelse
Functional test of computer cabinet doorsLang-beskrivelse
Check whether the cabinet doors close easily and tightly.Se dok. 2000006700 "Operating and Service Manual Generic
Master CCF Cabinets" kap 8.3.2 "Functional test of computer cabinet doors" på side 67 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV TK-F
Oppgave: 1080
Oppgavebeskrivelse
Visual inspection of cables and connectorsLang-beskrivelse
1) Check whether the earthing cables are connected from the cabinet doors to the cabinet frame.2) Check whether the earthing cable of the cabinet is fixed and not torn off.
3) Check whether the contact clips and cable straps are fixed properly.
4) Check whether the incoming and outgoing cables are laid and fixed properly.
5) Check whether all connectors are plugged in properly, fixed and labeled.
Se dok. 2000006700 "Operating and Service Manual Generic
Master CCF Cabinets" kap 8.3.3 "Visual inspection of cables and connectors" på side 68 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Lav
- Type FV TK-V
Oppgave: 1090
Oppgavebeskrivelse
Visual inspection of CoolBlastT 230V HP fan assemblyLang-beskrivelse
1) Check whether the fan assembly is operational: the green LED “system ok” on the front of the fan must light up.2) Check that the fan speed operates in the required range: the red LED on the front of the fan is off.
3) Check whether the fan assembly is making unusual noises.
Se dok. 2000006700 "Operating and Service Manual Generic
Master CCF Cabinets" kap 8.3.3 "Visual inspection of CoolBlastT 230V HP fan assembly" på side 68 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Lav
- Type FV TK-V
Oppgave: 1100
Oppgavebeskrivelse
Visual inspection of AC115-230V/DC24V fan assemblyLang-beskrivelse
1) Check whether the fan assembly is operational: the green LED on the front of the fan must light up.2) Check that the fan speed operates in the required range: the red LED on the front of the fan is off.
3) Check whether the fan assembly is making unusual noises.
Se dok. 2000006700 "Operating and Service Manual Generic
Master CCF Cabinets" kap 8.3.3 "Visual inspection of cables and connectors" på side 69 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Lav
- Type FV TK-V
Oppgave: 1110
Oppgavebeskrivelse
Functional test of AC115-230V/DC24V fan assemblyLang-beskrivelse
Press the blue button. The red LED must light up.Se dok. 2000006700 "Operating and Service Manual Generic
Master CCF Cabinets" kap 8.3.3 "Functional test of AC115-230V/DC24V fan assembly" på side 70 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Høy
- Type FV TK-F
Oppgave: 1120
Oppgavebeskrivelse
Central system software: Renew certificatesLang-beskrivelse
Before the SiPass certificates expire (default every 1170 day), the certificates need to be renewed. Contact Siemens Mobility support.Se dok. 2000000381 "Drifts- og vedlikeholdsmanual tilgangskontrollsystem, distribuerte komponenter", kapittel 6.5.7 "Oppdatering av fastvare for ACC-AP-kontroller" på side 133 for prosedyre.
- Intervall 36 md
- Myndighetsnivå Lav
- Type FV PO