Kontroll etter sporarbeid på kassesville CMB12, enkel kryssveksel, ERTMS (ES)

SA-ITC-0000-04-ES

ES

Oppgave Oppgavebeskrivelse Lang-beskrivelse Intervall Myndighetsnivå Type FV
1000 Kontroll etter sporarbeid After trackwork is done, visually inspect all tie plates, the pawls and the point machine for damage.
Throw the points once to each direction and check that the end position is reached.
Perform a 3 mm test see manual.
Check that the yellow marks still match as shown to indicate that the position of the ITS 710 on the rail is unchanged.
Se dok. 2000007831 "Vedlikeholdsmanual Switchguard ITS 710 for enkel kryssveksel" kap 5.6.13 "Utførelse av 3mm test" på side 187 for prosedyre.
ES Høy TK-V

Oppgave: 1000

Oppgavebeskrivelse

Kontroll etter sporarbeid

Lang-beskrivelse

After trackwork is done, visually inspect all tie plates, the pawls and the point machine for damage.
Throw the points once to each direction and check that the end position is reached.
Perform a 3 mm test see manual.
Check that the yellow marks still match as shown to indicate that the position of the ITS 710 on the rail is unchanged.
Se dok. 2000007831 "Vedlikeholdsmanual Switchguard ITS 710 for enkel kryssveksel" kap 5.6.13 "Utførelse av 3mm test" på side 187 for prosedyre.
  • Intervall ES
  • Myndighetsnivå Høy
  • Type FV TK-V